  1. Planning 3: Prioritization

    Slide 1 - Planning 3: Prioritization

    • Emerson Murphy-Hill
    • Creative Commons Attribution 4.0 License.
    • Material Produced by NCSU Software Engineering Faculty.
  2. Coming up with the plan

    Slide 2 - Coming up with the plan

    • Desired
    • Features
  3. Prioritization

    Slide 3 - Prioritization

    • Driven by customer, in conjunction with developer
    • Choose features to fill up velocity of iteration, based on:
    • Desirability of the feature to a broad base of customers or users
    • Desirability of a feature to a small number of important customers or users
    • The cohesiveness of the story in relation to other stories. Example:
    • “Zoom in” a high priority feature
    • “Zoom out” not a high priority feature
    • But it becomes one relative to “Zoom in”
  4. Priorities

    Slide 4 - Priorities

    • High
    • “Give us these stories to provide a minimal working system.”
    • Medium
    • “We need these stories to complete this system.”
    • Low
    • “Bells and whistles? Which stories can come later?”
  5. Coming up with the plan

    Slide 5 - Coming up with the plan

    • Desired
    • Features
    • 30 story points
    • 6 iterations
    • 5 story points/two- week iteration
    • October 30